Road Improvements

Capital Road Investment 2022-2024

The Town financed $5 million for a road/bridge improvement plan during 2022-2024. This significant investment raised the overall level of road conditions throughout the Town on the PASER scale (pavement surface evaluation and rating). Before the work began, the overall PASER rating of Town roads was 5.85 / 10. Following completion of the three-year construction period, the rating increased to 7.49 / 10. The tax impact of the work is estimated at $0.31/$1,000 of assessed value, which was seen on tax bills beginning in December of 2022. Multiple grants were obtained during the capital investment period, including grant funding towards Cedar Sauk Road, Columbia Road, Sherman Road, and the Covered Bridge automobile bridge. Additional cost-sharing projects with neighboring communities included Susan Lane, Sycamore Drive, and Hilltop Drive through intergovernmental agreements. Savings that were realized through these efforts allowed for funds to be allocated toward modernizing the Town equipment fleet. Efforts continue to obtain additional grant funding for capital projects.

Current Road Construction Projects

County, State and Inter-Municipal projects are also shown, but are not managed by the Town.

 

Project Contact 2026 Town Managed Road Projects
Adam Monticelli
Director of Public Works
Phone: (262) 377-4509
Email: Adam

Project Summary: No major Town roadway resurfacing is planned for this construction year due the extent of the resurfacing work 2022-2024. This allowed time to analyze the overall condition rating of Town roads following the work to see the positive impact the investment had on the PASER rating for the Finance Committee and Town Board to plan for future investments. The Town Public Works Crew will be completing the following projects this spring and summer:

  • Shoulder work
  • Minor culvert replacements
  • Drainage excavation and grading
  • Bridge repairs
  • Noxious weed removal
  • Sealing asphalt roadways that were recently resurfaced
  • Crack filling
  • Minor asphalt patching/pothole filling

Current Project Status: Ongoing

 

 

Project Contact 2026 Ozaukee County Projects 
Jon Edgren
Oz. Co. Highway Dept.
Phone: (262) 284-8331
Email Jon Edgren
Project Summary:  Ozaukee County is planning on conducting a 2.5” overlay of 5.1-miles of roadway on CTH I from Lilac Lane to STH 33 [Town of Cedarburg & Saukville]. Construction is anticipated for summer of 2026. Please contact Ozaukee County Highway Department with any questions.

Current Project Status: To be updated when information is received from Ozaukee County

 

Project Contact

Nguyen Ly

(262) 548-8739

Nguyen.Ly@dot.wi.gov

Project Summary: The Wisconsin Department of Transportation (WisDOT) is proposing future roadway improvements along WIS 60 in Ozaukee County.

State of Wisconsin Managed Project

Scheduled for 2029

WisDOT Project website: Click here to view the webpage.

This project is tentatively scheduled for 2029 construction.  WIS 60, from Five Corners Drive to 1st Avenue, will be resurfaced and the bridge over Cedar Creek will receive a surface sealer. The traffic signals will be replaced at the intersections of WIS 60 with WIS 181, County I, Keup Road. Sidewalk ramps throughout the project will be upgraded to ADA standards, and new sidewalk will be constructed at the southwest quadrant of the intersection of WIS 60 and Washington Avenue. Culverts and guardrails will be replaced, and drainage work will include inlet replacements and grading around the bridge.

WIS 60 will be open to traffic during construction.